Tata Sons Chairman N Chandrasekaran initiated the first equipment trial for the upcoming cold rolling mill and pellet plant projects of Tata Steel at Kalinganagar, Odisha through the digital twin interface.
This signifies the completion of a major milestone for the Kalinganagar expansion project from three million tpa to eight million tpa.
He also inaugurated an integrated sinter plant operation centre (i-SPOC) at Information Technology and System (ITS) Building inside Jamshedpur Works.
The three current operating sinter plant units have been merged into a far-site single operation control centre.