Tata Refractories plans modernisationIllustrative image – not actual.

Tata Refractories has outlined a Rs.84 crore modernization-cum-expansion plan, that would be spread over five years.

 

The objective of the plan is to enhance the company’s manufacturing facility at Belpahar in Orissa’s Jharsuguda district, from the present 1.23 lakh tpa to 3 lakh tpa.

 

During the current fiscal year, an investment of Rs.38 crore would be made to step up capacity to 1.75 lakh tpa. The final capacity of 3 lakh tpa would be attained by March 2008. For the year 2007-08, the company has targeted sales turnover of Rs.500 crore as against Rs.244 crore in 2002-03.  

 

The overall investment would be spread over the areas of quality and yield improvement (58 per cent), stepping up productivity (30 per cent) and improving information technology facilities (12 per cent.)