Tata Projects achieves 110 km stretch of Surathani-Phuket transmission lineIllustrative image – not actual.
Tata Projects has completed 110 km stretch of the 200 km Surathani-Phuket transmission line project in Thailand.

The 500 kV transmission line is an achievement since it passes through thick jungles and mountainous terrain. The project will bring additional electricity to Phuket, thereby improving the lives of citizens.

Of the Tata Projects-led consortium’s 110 km stretch, about 80 km was executed by Tata Projects and the remaining by its partner. The company utilised drone technology for stringing of transmission lines thereby reducing timeframe and avoiding manual work.

All tower foundations were completed using ready mixed concrete which is a symbol of 100 percent concrete quality. Additionally, Tata Projects also prepared approach roads for ready mixed concrete trucks.

A unique aspect of the project is that it is the first 500 kV transmission line passing from Phang-nga province in Southern Thailand, bordering the Andaman Sea on the West Coast of the Malay Peninsula.

Prior to this, Tata Projects-led consortium had executed an 80 km stretch of 500 kV Roi Et 2-Chaiyaphum 2 Transmission Line project in August 2019. It was the company’s first successfully executed transmission line project in Thailand.