Illustrative image – not actual.Tata Power's 120 MW Jojobera power unit is scheduled to be commissioned by end-October 2005. The unit was synchronized to grid on 23 September 2005.
With the commissioning of this unit (Unit No.4], the total capacity of the Jojobera power plant will stand enhanced to 427.5 MW [1x67.5 + 3x120].
Bharat Heavy Electricals was the EPC contractor of the project, and had targeted (in early August 2005) to synchronize Unit No.4 by 31 August 2005.
Also See:
