Tata Power to commission two units of Mundra UMPP by 2012Illustrative image – not actual.

Tata Power is planning to bring into operations the first two units of its 4,000 MW Mundra Ultra Mega Power Project (UMPP) in Gujarat by 2012. The Mundra UMPP is likely to be fully commissioned by December 2013.

So far, the company has completed 30 per cent work on the project. It is likely to commission the first unit in September 2011 and subsequently other units will follow at an interval of five months each. The second unit is expected to go on stream by February 2012.

The company is likely to import 12 million tonne of coal from an Indonesian coal block, where it has acquired 30 per cent stake. Nearly, half of the fuel requirement of the project is expected to be sourced from these mines.

The project entailing an investment of Rs 17,000 crore is being funded through a debt and equity ratio of 75:25.

Also See:

Tata Power gets breather as land owners agree for land acquisition (18-Aug-09)

Related Links:
Project profile

 