Illustrative image – not actual.Tata Power Co (TPC) has sought
approval from Maharashtra Electricity Regulatory Commission
(MERC) for its Rs.455 crore capital expenditure programme which
includes expanding wind generation capacity, developing a
multi-fuel jetty and relocating the cooling water system at
Trombay thermal power station.
TPC plans to invest Rs.140 crore to develop a 35 MW wind farm for
which, a site has been identified in Dhule district. Work on the
and may be taken up for implementation in 2004-05. The generated
electricity will be wheeled to licensed area from the point of
generation. It may be noted that TPC currently operates a 17 MW
wind farm in its licensed area in Mumbai.
A multifuel jetty is being developed at Trombay on a build, own,
operate and transfer (BOOT) basis. The 210 mtrs long berth is
being constructed in the main drainage channel of Mumbai harbour,
located 3.5 km from the power station. The berth, entailing an
investment of Rs.180 crore, would help do away with the present
system of multiple handling of coal. An expenditure of Rs.35
crore is being incurred in the current fiscal.
A capital investment of Rs.150 crore is envisaged on relocation
of the cooling tower system at Trombay TPS. During the current
year, an expenditure of Rs.15 crore is being incurred on the
scheme.
Further, the boiler of Unit 4 of the TPS is being modified to
suit the coal firing requirements. It may be recalled that TPC is
in the process converting units 4 & 5 at Trombay TPS from
naphtha based combined cycle units to coal based units.