Tata Power has completed construction of the Unit II of 800 MW of its Mundra ultra mega power project (UMPP) in Gujarat.

The company has synchronised the Unit II 800 MW of 4,000 MW Mundra UMPP. With synchronisation of the Unit II, the thermal power generation capacity of Tata Power stands at 5,247 MW and the generation through clean sources such as hydro, wind and solar stands at 852 MW. Tata Power's total generation capacity now stands at 6,099 MW.
 
The Unit I of Mundra UMPP was commissioned in March 2012.
 