Tariff charge of Dabhol Phase II not to exceed Rs.4 per unitIllustrative image – not actual.

Dabhol Power Company president, Neil Mcgregor has clarified that the per unit cost of power generated by its plant in Dabhol (Ratnagiri district of Maharashtra) will not exceed Rs.4 per unit on completion of its second unit by December 2001. The company is currently charging MSEB Rs.4.90 per unit of power supplied.

 

It was reported that the cost of per unit from the Dabhol plant would increase to Rs.7.80 per unit when the phase II of the project will become operational in December 2001. Denying this allegation the company clarified that on completion of the phase II the entire unit would start using LNG as fuel. As LNG is around 20 per cent cheaper than naphtha, which it is currently using as fuel, the company is confident that the per unit cost of power supplied would not exceed Rs.4 per unit.

 

← All latest storiesBack to top →