Illustrative image – not actual.The 220 MW naphtha-based Tannirbhavi Power Project is expected to commence operations soon. This is India’s first-ever power project that has been mounted on a barge.
The barge housing the power plant has reportedly arrived at the Mangalore Port. The barge would be soon shifted to its designated site along the banks of the Gurupura river.
The barge has linear dimensions of 160 m x 55.2 m and weighs 16,779 tonnes, gross of the power plant. The project cost is estimated at Rs.900 crore
The project was cleared by the Karnataka State government in 1995. Since then, the project has undergone several transformations including a change in project promoters. The project, when conceived, was to be implemented by US-based Chicago Power Company. The project is now being implemented by Tanir Bavi Power Co Pvt Ltd, a 51:49 joint venture between the GMR Group of India and the US-based PSEG Group.