Illustrative image – not actual.Tanir Bhavi Power Company (TBPC) announced,
on 11 June 2001, that it has commenced simple cycle operations of 170 MW of its
220 MW combined-cycle barge-mounted power plant located south of Mangalore in
Karnataka. The plant is expected to start combined cycle production by July
2001.
TBPC is a joint venture between PSEG
Global of the US (holding 74 per cent of the equity) and the GMR Vasavi group
that holds the remainder.
The barge-mounted power plant was
assembled by Hyundai in Korea and then sailed to the Mangalore coast. The power
project has a power purchase agreement with the Karnataka State Electricity
Board (KSEB) and escrow support from the Karnataka Power Transmission
Corporation Ltd.
The Tanir Bhavi project is PSEG Global’s
second power project in India. Its first project – the 330 MW Pillai
Perumalnallur project in Tamil Nadu – began operations in April 2001.