Illustrative image – not actual.The Tamil Nadu government has postponed its plan to develop Cuddalore into a mega all-weather port with an investment of Rs.1,200 crore. It was felt that the project would not be commercially viable, since the port could not attract enough guaranteed cargo to make such a huge investment worthwhile. The port would need at least 10 to 12 million tonnes of cargo annually to make the project commercially viable.
The state government had invited bids for the development of
the port over a year ago and shortlisted some parties. However, the bids were
found to be unviable and the plan was postponed. Feasibility studies done
earlier had indicated that the development of the port depended on setting up
of major industrial activities, including movement of coal and generation of
power. However, the Cuddalore Power Company’s (CPCL) plan to set up a 1,320 MW
coal-based thermal power plant, had not materialised. Also, coal movement to
Cuddalore port in a feasible volume could take place only after Ennore port
reaches full operational capabilities. If this happens, coal meant for Mettur,
could be diverted to Cuddalore port. However, the Ennore port is not yet fully
developed.
It was also proposed to have a private jetty at Cuddalore,
for handling coal by the CPCL for its power project. This too, has not
materialised. Earlier, it was felt that Cuddalore offered an ideal location for
transhipment of cargo, assuming that several industrial units would be setting
up operations in and around the port area.
As far as expenditure was concerned, around 60 to 70 per
cent of the cost for developing Cuddalore port would have to be spent in
improving the water basin to facilitate the movement of big vessels. Most of
the expenditure would be towards break water construction and capital dredging
of enclosed area and navigation of channels.