Tamil Nadu seeks more time for intra-state green energy corridorIllustrative image – not actual.
The government of Tamil Nadu has sought the Union Ministry of Power’s approval to extend the schedule for setting up power transmission network for renewable energy projects in the state.

The original deadline for setting up the intra-state green energy corridor was March 2017, which was extended to March 2019. The state wants the new deadline to be March 2020.

The state needs more time to tackle the right-of-way (RoW) issues which are impeding the deployment of the green energy corridor within the state. Currently, there are 70 RoW issues and the physical progress of the project is about 83 percent.

As much as 63 RoW issues are related to the Ingur-Arasur 400 kV substation and the rest pertain to Cuddalore-SP Koil (Veerapuram) transmission line. These challenges are blocking the installation of 665 circuit km of power lines meant to evacuate electricity from renewable generation plants.

Intra-state transmission schemes are to be funded as 20 percent equity of the state government, 40 percent grant from the Central government and 40 percent soft loan. The total project cost in Tamil Nadu was initially estimated to be Rs 1,593 crore.

The state has signed a loan agreement from KfW, Germany, for a financial assistance of EUR 76 million for the project. The Solar Energy Corporation of India (SECI) is planning to build a land pool to accommodate 50 GW of renewable plants to solve the land-availability issue.

With 12,125 GW installed capacity, more than 15 percent of the country’s renewable energy projects are located in Tamil Nadu.