Illustrative image – not actual.The Cabinet, yesterday, approved setting up an inter-state power transmission system in Tamil Nadu with an investment of Rs 1,593 crore.
The power transmission project was approved by the Cabinet Committee on Economic Affairs (CCEA) chaired by the Prime Minister, Narendra Modi, and will be completed within three years.
The Tamil Nadu project will include the establishment of a 400 kV grid substation at Thannampatty; augmentation of various 230 kV grid substations; and associated transmission systems.
The cost of creating the infrastructure is proposed to be met through KfW loan (40 per cent), NCEF grant (40 per cent) and state contribution (20 per cent).
In Tamil Nadu, a large number of wind projects are already working or under installation and the existing power transmission infrastructure is insufficient to cater to the existing and new renewable energy installations.
The intra-state transmission system will be ready by 2016-17 for evacuation of renewable power.
More Project Info: