Illustrative image – not actual.Power Grid Corporation has received clearance from public investment board (PIB) for its investment in Tala transmission project.
The project, which is expected to cost Rs.1100 crore, is a joint venture between power grid and Tata power and would be funded in the debt equity ratio of 70:30. The Tala transmission project involves setting up transmission lines from Bhutan to Delhi for carrying the surplus power from 1020 MW hydroelectric plant in Bhutan to power deficient northern grid.
The project would be implemented in three stages and is expected to be operational by 2004-05.