SWR completes 65 percent work on track-doubling projectIllustrative image – not actual.
The South Western Railway (SWR) has completed nearly 65 percent of the track-doubling project on the 352.5 km Hospet-Hubli-Londa-Vasco route.

Another 36 km is targeted to be commissioned for 2017-18. Phase I of the project consists of doubling of the 245 km track between Hospet and Tinaighat.

Eighty km of the 97 km stretch of Tinaighat-Castle Rock and Kulem-Vasco section lie within Goa, while 17 km is located in Karnataka.

The estimated cost of track doubling of this stretch, which will be executed during the second phase, is Rs 1,198 crore as per a preliminary engineering survey.The SWR has so far incurred an expenditure of over Rs 700 crore.

The project is expected to boost movement of imported coal from the Mormugao port to steel industries and upcoming thermal power plants in Karnataka. The track is also expected to increase passenger trains connecting tourist destinations to Goa.

← All latest storiesBack to top →