Illustrative image – not actual.The
copper cathodes project of SWIL is finally set for commissioning. According to
company sources, trial production is likely to commence in June 2002. Commercial
production may begin by September and full scale commercial operations may stabilise
by end of the year.
The
company is setting up the copper smelter with refining facilities at Jhagadia
in Bharuch district of Gujarat. The plant will have a smelting capacity of
70,000 tonnes and refining capacity of 50,000 tonnes.
The
project has been beset by time and cost overruns, primarily due to the company’s
inability to raise funds for the project. Meantime, the cost of the project escalated
from its original estimate of Rs.464 crore to around Rs.1,185 crore (US$ 242.3
million). The project was delayed for commissioning by three years.