Illustrative image – not actual.Suzlon Energy on 6 January 2011 signed an agreement with Hindustan Zinc, a Vedanta Group company, for setting up wind farms.
Suzlon is to set up, operate and maintain 150 MW of wind farms for Hindustan Zinc, for $191 million (approx Rs 859.5 crore). The project is to be completed in phased manner. These wind farms are to come up in Karnataka, Rajasthan, Tamil Nadu and Maharashtra.
Under the Phase I, wind farms with a capacity of 50 MW are to be set up with completion by March 2011. The second and final phase of 100 MW will be progressively completed by September 2011.
Suzlon will be supplying a mix of its S82-1.5 MW and S88-2.1 MW wind turbine models. The power generated will be purchased by the respective state's distribution utilities at the prevailing feed-in tariff under a long term PPA.