Illustrative image – not actual.The proposed 4,000 MW ultra mega power project (UMPP) in Surguja district of Chhattisgarh has been delayed by another two months.
The last date of submission of technical bids for the project has been extended till 8 March 2011 from 7 January 2011.
Power Finance Corporation is the nodal agency for the project. Initially, the UMPP was allocated two blocks at Puta and Parogia but the MoEF refused to approve mining as the blocks lay in forest land that has been declared as a 'no-go' area.