Illustrative image – not actual.Surendra Mining Industries' steel plant at Bonai in Sundergarh district is expected to be commissioned by end-2009.
The detailed project report (DPR) is under preparation after which the company will approach its bankers for financing the project. While total 200 acres of land is required for the plant, the company's existing sponge iron plant has about 70 acres. Land acquisition of the remaining land is underway. The company has sought the technical assistance of MN Dastur for setting up the steel plant.
The project will be implemented in phases. In Phase I, the steel plant will include furnace, captive power plant and continuous casting machines (CCM), which will make it possible to manufacture billets. Work on 16 MW captive power plant is likely to commence by October 2007 with completion scheduled by end-2008. Phase II of the project will include blast furnace and sinter plant.