Suratgarh TPS commissionedIllustrative image – not actual.

With the synchronisation of 250 MW fifth unit, the 1,250 (5 x 250) MW Suratgarh TPS has been completed. The fifth unit was synchronised by Bharat Heavy Electricals (BHEL) in a record time of 12 hours as against the standard time of two to four weeks.

 

The project was cleared by CEA in 2001 at an estimated completed cost of Rs.752 crore. The project has been funded by a mix of debt and equity in the ratio of 80:20.  Power Finance Corporation sanctioned a loan of Rs.448 crore and another Rs.150 crore has been provided by banks and financial institutions. Stage II of the project, constituting Units 3 & 4,  was commissioned in March 2002 -- six months ahead of schedule.

 