Suratgarh Power Station's fourth unit commissionedIllustrative image – not actual.

Bharat Heavy Electricals (BHEL) has commissioned the 250 MW fourth unit of the Suratgarh thermal power station, in Rajasthan, ahead of schedule. This unit, which is part of stage II of Suratgarh power station project, is expected to improve the power situation in the power deficit state.

 

According to BHEL, the use of latest techniques and deployment of state-of-the-art construction aid, helped it to commission the unit ahead of schedule.

 

Earlier, BHEL had completed the third unit of 250 MW, (part of stage II of the project), 5 months ahead of schedule, while the first and second units (of 250 MW each) comprising stage I, were completed in 1988 and 2000, respectively.

 

Rajasthan Rajya Vidyut Utpadan Nigam, which is implementing the Suratgarh project, has planned stage III for the project, i.e. a fifth unit of 250 MW. This unit is also expected to be completed ahead of schedule, in 2002-03.