Illustrative image – not actual.Surana Solar has emerged as the lowest bidder for the rooftop installation of five MW solar power generating units under the Kakinada Smart City Project in Andhra Pradesh.
The project will be executed in six months from the date of agreement.
The company will supply power to Kakinada Corporation at Rs 5.25 per unit. The overall cost of the project is estimated to be Rs 5 crore per MW.
The company has also received an order from Tejas India Solar Energy to supply solar modules for a three MW solar power plant located at Kodakandla village in Gajwel mandal of Medak district of Telangana. The cost of project is Rs 14 crore.