STP work to begin soonIllustrative image – not actual.
The sewage treatment plant (STP), part of the multi-crore sewerage project being implemented under the Kerala Sustainable Urban Development Project (KSUDP), coming up near Sarovaram in Kozhikode, will begin soon.

 

KSUDP has signed an agreement with UEM India for constructing the 13.5 MLD STP and for maintaining it for a period of five years. The work was awarded to UEM India for Rs 29.80 crore with a completion period of 18 months.

 

There are concerns over the delay in getting the proposed site cleared for the construction work, which is presently used by Japan International Cooperation Agency (JICA). Kerala Water Authority has already issued an ultimatum to the authorities concerned to clear the site and hand it over for STP construction, by 20 April.

 

The STP is a major component of the sewerage project being implemented with aid from the Asian Development Bank (ADB). The initial phase includes laying of 67.7 km pipes to carry sewage, construction of pumping and lifting stations, among other work.

 

More project Info:
Sewage Treatment Plant (Kozhikode)

← All latest storiesBack to top →