Illustrative image – not actual.On 16 September 2007, Union Power Minister, Mr Sushilkumar Shinde laid the foundation stone for NTPC's 1,000 MW (2x500 MW) has Simhadri super thermal power project (Stage II) in Visakhapatnam district of Andhra Pradesh.
The Stage-II of the project will be built at an estimated cost of Rs.5,038 crore and is slated to be completed by 2010-11. The cost from the unit will be Rs.2.3 per kwh.
The first 500 MW of the 1,000 MW Simhadri power project (Stage I) near Visakhapatnam had been commissioned in 39 months and the second 500 MW unit had also been commissioned in 45 months' time.