Illustrative image – not actual.Steel Authority of India's Director Personnel & In-charge-of its Raw Materials Division, Mr G Ojha, on 27 August 2008, laid the foundation stone for the Rs.120 crore iron ore mines augmentation project at Bolani in Orissa.
The expansion project is aimed at augmenting the iron ore loading capacity at the Bolani mines from the present level of 3.9 million tpa to 10 million tpa. The project has been divided into two parts. The first part covers loading facilities and includes installation of the reclaimer, stacker, conveyors and a new stacking yard, whereas the second part of the scheme will cover railway track modification, overhead electrical work, signalling and telecommunication, etc.
The Centre for Engineering & Technology, an in-house division of SAIL, has been appointed as consultant for the entire project.