Illustrative image – not actual.The agreement is for Batch 13, won at energy transmission auction held by ANEEL, a Brazilian Electricity Regulatory Agency. The completion of the project is expected in March 2023.
The project includes construction of three energy transmission lines totalling 316 km, two substations and 1,544 MVA transformation capacity, with annual allowed revenue of around Rs 133.98 crore.
Sterlite Power develops power transmission infrastructure and has projects exceeding 12,500 km in circuits and 20,500 MVA in India and Brazil.