The power ministry’s capacity addition programme for the ongoing Five Year Plan period seems to be progressing well, as suggested by present trends.

 

As per the original estimates, the country was expected to install 41,110 MW of additional power capacity — comprising 25,417 MW (61.8 per cent) of thermal, 14,393 MW (35 per cent) of hydro and 1,300 MW (3.2 per cent) of nuclear power — during the Tenth Plan period (April 2002 to March 2007.). This incremental capacity represented nearly 40 per cent of the country’s installed capacity existing at the beginning of the Plan period.

 

Of the 25417 MW of thermal capacity, by far the most important component of India’s power sector, as much as 50 per cent is expected to come from public sector units, mainly NTPC. The remaining would come, roughly equally, from state-owned enterprises and private sector companies.

 

For the current year, 2003-04, the power ministry has targeted thermal capacity addition of 1,437 MW, higher than the 1,348 MW envisioned at the beginning of the Plan period. At the end of the first quarter, capacity of 318 MW was commissioned – the 250 MW Suratgarh Thermal Power Station (Stage 3) of RRUVNL, a Rajasthan government undertaking, being the most important fruition. Till end-June 2003, no power project from the Central power utilities or the private sector fructified. In the remaining three quarters of 2003-04, Central PSUs are expected to add 710 MW and state enterprises, 357 MW, which is over and above the 318 MW already installed. A solitary 52.8 MW gas-based project is expected from the private sector. The project in question is the Valantharvi project promoted by Arkay Energy of Tamil Nadu. The thermal power capacity addition target for 2003-04 is most likely to be met.

 

With private sector participation continuing to elude India’s power sector, the success of thermal capacity build-up hinges on National Thermal Power Corporation. For the Tenth Five Year Plan period, NTPC has targeted to add 9,370 MW of capacity through nine projects, entailing capital investment of Rs.60,000 crore. Of this capacity, 1,000 MW was added till June 2003. During July 2003, NTPC tied up funds worth Rs.13,000 crore to support its expansion plans. Banks and financial institutions have committed funds worth Rs.7,000 crore while LIC has promised another Rs.6,000 crore. Besides, NTPC expects to raise close to Rs.6,000 crore through bonds. For 2003-04, NTPC has planned capital expenditure of Rs.4,500 crore. The 500 MW Talcher Super Thermal Project in Orissa is NTPC’s only project headed for completion in this year. NTPC is expected to witness heavy capacity augmentation (over 6,000 MW) during the concluding two years of the ongoing Plan period, 2005-06 and 2006-07.

 

During 2002-03, thermal power capacity addition was quite satisfactory. The power ministry had envisaged fresh capacity of 3,502 MW — Central PSUs (920 MW), state-owned enterprises (790 MW) and private sector (1,792 MW). The estimate for private sector capacity addition included the 1444 MW Phase II of the beleaguered Dabhol Power Company (DPC). Even today, uncertainty shrouds the fate of 740 MW Phase I, which was shut down in May 2001 and the commissioning of Phase II, in which 93 per cent of physical work is complete. It may be mentioned that M N Rothschild, financial advisor to DPC, recently recommended a “comprehensive” solution rather than a piecemeal approach to the stymied project. With resumption of Phase I now being ruled out, commissioning of  Phase II is pushed further into the unknown.

 

Excluding DPC, the target for 2002-03 works out to 2,058 MW, against which 2,223 MW was added. Central PSUs gave 1,210 MW of fresh thermal capacity (NTPC, 1,000 MW and Neyveli Lignite, 210 MW), while state-run entities contributed 665 MW. The private sector added 348 MW through three projects.

 

As of June 2003, India’s total power capacity was 105,135 MW, out of which thermal capacity was 75619 MW. If ongoing projects progress in line with current thinking, the country’s thermal capacity would stand enhanced to 76488 MW by end-March 2004.

 

Meanwhile, power generation grew by 4.2 per cent in the first quarter of 2003-04. The country’s total power generation is likely to touch 572.9 billion units during the current fiscal, 7.9 per cent higher than the actual generation of 530.8 billion units in 2002-03. Hydel power is expected to make a higher contribution, thanks to the healthy South-west monsoon this year.

 