The power ministry’s capacity
addition programme for the ongoing Five Year Plan period seems to be
progressing well, as suggested by present trends.
As per the original estimates,
the country was expected to install 41,110 MW of additional power capacity —
comprising 25,417 MW (61.8 per cent) of thermal, 14,393 MW (35 per cent) of
hydro and 1,300 MW (3.2 per cent) of nuclear power — during the Tenth Plan
period (April 2002 to March 2007.). This incremental capacity represented
nearly 40 per cent of the country’s installed capacity existing at the
beginning of the Plan period.
Of the 25417 MW of thermal
capacity, by far the most important component of India’s power sector, as much
as 50 per cent is expected to come from public sector units, mainly NTPC. The
remaining would come, roughly equally, from state-owned enterprises and private
sector companies.
For the current year, 2003-04, the
power ministry has targeted thermal capacity addition of 1,437 MW, higher than
the 1,348 MW envisioned at the beginning of the Plan period. At the end of the
first quarter, capacity of 318 MW was commissioned – the 250 MW Suratgarh
Thermal Power Station (Stage 3) of RRUVNL, a Rajasthan government undertaking,
being the most important fruition. Till end-June 2003, no power project from
the Central power utilities or the private sector fructified. In the remaining
three quarters of 2003-04, Central PSUs are expected to add 710 MW and state enterprises,
357 MW, which is over and above the 318 MW already installed. A solitary 52.8
MW gas-based project is expected from the private sector. The project in
question is the Valantharvi project promoted by Arkay Energy of Tamil Nadu. The
thermal power capacity addition target for 2003-04 is most likely to be met.
With private sector participation
continuing to elude India’s power sector, the success of thermal capacity
build-up hinges on National Thermal Power Corporation. For the Tenth Five Year
Plan period, NTPC has targeted to add 9,370 MW of capacity through nine
projects, entailing capital investment of Rs.60,000 crore. Of this capacity,
1,000 MW was added till June 2003. During July 2003, NTPC tied up funds worth
Rs.13,000 crore to support its expansion plans. Banks and financial
institutions have committed funds worth Rs.7,000 crore while LIC has promised
another Rs.6,000 crore. Besides, NTPC expects to raise close to Rs.6,000 crore
through bonds. For 2003-04, NTPC has planned capital expenditure of Rs.4,500
crore. The 500 MW Talcher Super Thermal Project in Orissa is NTPC’s only
project headed for completion in this year. NTPC is expected to witness heavy
capacity augmentation (over 6,000 MW) during the concluding two years of the
ongoing Plan period, 2005-06 and 2006-07.
During 2002-03, thermal power capacity
addition was quite satisfactory. The power ministry had envisaged fresh
capacity of 3,502 MW — Central PSUs (920 MW), state-owned enterprises (790 MW)
and private sector (1,792 MW). The estimate for private sector capacity
addition included the 1444 MW Phase II of the beleaguered Dabhol Power Company
(DPC). Even today, uncertainty shrouds the fate of 740 MW Phase I, which was
shut down in May 2001 and the commissioning of Phase II, in which 93 per cent
of physical work is complete. It may be mentioned that M N Rothschild,
financial advisor to DPC, recently recommended a “comprehensive” solution
rather than a piecemeal approach to the stymied project. With resumption of
Phase I now being ruled out, commissioning of
Phase II is pushed further into the unknown.
Excluding DPC, the target for 2002-03
works out to 2,058 MW, against which 2,223 MW was added. Central PSUs gave
1,210 MW of fresh thermal capacity (NTPC, 1,000 MW and Neyveli Lignite, 210
MW), while state-run entities contributed 665 MW. The private sector added 348
MW through three projects.
As of June 2003, India’s total power
capacity was 105,135 MW, out of which thermal capacity was 75619 MW. If ongoing
projects progress in line with current thinking, the country’s thermal capacity
would stand enhanced to 76488 MW by end-March 2004.
Meanwhile, power generation grew by 4.2
per cent in the first quarter of 2003-04. The country’s total power generation
is likely to touch 572.9 billion units during the current fiscal, 7.9 per cent
higher than the actual generation of 530.8 billion units in 2002-03. Hydel
power is expected to make a higher contribution, thanks to the healthy
South-west monsoon this year.