Illustrative image – not actual.Reliance Petroleum on 19 October 2006 announced that the it has achieved impressive all-round progress in implementation of its 27 million tpa refinery at Jamnagar; it is scheduled to complete by December 2008.
The following are highlights of the project progress during the quarter ending September 2006.
- Entire land of 1,700 acres acquired
- Basic engineering completed and nearly 50 per cent of detailed engineering completed
- More than 7,500 engineers are working on the project, across locations globally.
- All long lead and critical equipments ordered
- Major construction contracts awarded
- Civil and piping works progressing
- Project transitioned from engineering phase to construction phase
- Over 230,000 cubic meters of concreting completed
- Project geared to receive a peak workforce of over 100,000 people in the coming months
- Cumulative expenditure on project stood at Rs.4,054 crore as against Rs.7,266 crore anticipated. The apparent shortfall was due to non-payment to certain contractors and service providers pending documentation work.
For more stories on the Jamnagar refinery project, click here.