Status report on Reliance Jamnagar refineryIllustrative image – not actual.

Reliance Petroleum on 19 October 2006 announced that the it has achieved impressive all-round progress in implementation of its 27 million tpa refinery at Jamnagar;  it is scheduled to complete by December 2008.

The following are highlights of the project progress during the quarter ending September 2006.

  • Entire land of 1,700 acres acquired
  • Basic engineering completed and nearly 50 per cent of detailed engineering completed
  • More than 7,500 engineers are working on the project, across locations globally.
  • All long lead and critical equipments ordered
  • Major construction contracts awarded
  • Civil and piping works progressing
  • Project transitioned from engineering phase to construction phase
  • Over 230,000 cubic meters of concreting completed
  • Project geared to receive a peak workforce of over 100,000 people in the coming months
  • Cumulative expenditure on project stood at Rs.4,054 crore as against Rs.7,266 crore anticipated. The apparent shortfall was due to non-payment to certain contractors and service providers pending documentation work.