Illustrative image – not actual.The Rajasthan Government on 21 July 2010 approved the proposed metro rail project in Jaipur to be implemented in two phases.
Phase I of the project is expected to cost Rs 1,250 crore while Phase II will cost around Rs 7,850 crore.
For the first phase, the state government will provide Rs 600 crore to the Jaipur Metro Rail Corporation (JMRC), which will also take a loan of about Rs 300 crore. Another Rs 150 crore is to be provided by Jaipur Development Authority while Housing Board and RIICO will shell out Rs 100 crore each.
The first phase is likely to connect Mansarovar to Chandpol, covering a distance of 9.5 km. DMRC will build the 9.5 km stretch. In this route, while nine km will be on an elevated track, the rest 0.5 km will be underground.
While work on the first phase is slated to be completed by June 2013, the second phase will take five years for completion. It will run between Panipech and Sitapura industrial area, covering 23 km.