The Water Resource Department (Maharashtra) has scrapped the contract for Kondhane dam project in Raigad district of the state.

The cost of the project had escalated from Rs 80.35 crore to Rs 435 crore, after the height of the dam was increased without any assessment. The department has written to the governor’s office stating that Instructions are issued to executive director, Konkan Irrigation Development Corporation, to terminate the contract for the original work of the dam as it was taken up without fulfilling the conditions mentioned in the administrative approval. It is proposed to take action against concerned officers after enquiry into the matter. The department has also cancelled the contract for the additional work given to the same contractor after the height of the dam was increased from 39 mtrs to 71 mtrs.