Illustrative image – not actual.Prism Cement's 2.5 million tpa clinker plant project at Satna received approval from the state government.
Recently, the company Board of Directors has also gave its nod to the Rs.1,200 crore cement clinker plant coming up at Satna in Madhya Pradesh. The Mumbai based Bhagvati Design is the engineering consultant for the project. Currently, land leveling work on the project is underway and the company is awaiting finalisation of civil contractor. Civil work on the project is expected to commence by this October with completion scheduled for March 2010.