The civic body is yet to finalize the starting point of the Rs 12000 crore coastal road project in Mumbai.
Civic officials are now revisting the plan and studying the feasibility of beginning the tunnel half a kilometer ahead of the Princess Street flyover instead of Tambe Chowk junction. This is likely to reduce the current 33.207 km length of the coastal road.
As per the original design project report (DPR), the coastal road was to begin from an undersea tunnel starting near NCPA and going up to Priyadarshini Park. This was, however, changed by the civic officials and later planned from near Tambe Chowk junction to Priyadarshini Park.
The civic body revealed that there were technical difficulties that were noticed while planning the tunnel from the Tambe Chowk. There were certain gradient issues and also the junction was curved which would have been an issue while construction. Owing to this they are looking to start it half a kilometer or more ahead of the Princess Street flyover that can also help solve the traffic issues on Marine Drive road during peak hours.
While the civic body has managed to get the approval of the Maharashtra Coastal Zone Management Authority (MCZMA) subject to compliance of various conditions and observations, the redesigning of the tunnel is likely to delay the project.