Illustrative image – not actual.SS Yamne Power has estimated a levelised tariff for its hydel power project on Yamne (left bank tributary of Siang river) river in Upper Siang district of Arunachal Pradesh.
The company has levelised the tariff of Rs 5.90/KWh for its 135 MW Yamne-I hydel power project. It will comprise three units of 45 MW each. The project has been estimated to cost Rs 1,662 crore and the proposed layout will provide 135 MW of peak power with generation of 602.10 GWh of electricity in a 90 per cent dependable year on a 95 per cent machine availability basis. The project feasibility report (PFR) has already been submitted to MoEF for specifying terms of reference for undertaking environment impact assessment studies on the project. The project is expected to be commissioned within the period of five years after receiving all requisite approvals.