Srisailam power project's first unit to be synchronised by December 2000Illustrative image – not actual.

The first unit of the Srisailam Left Bank Power Station Project coming up in Adhra Pradesh would to be synchronised by December 2000. The 900 MW power project is estimated to cost Rs.2,325 crore. This unit was to be commissioned by July 2000, but due to certain problems such as excess seepage during underground tunneling, the project has been delayed.

 

The Japan Bank for International Co-operation had extended a loan of Rs.1,902 crore for the first stage of the project. All the civil works connected with the project were in the final stages of completion.

 

The other five units were expected to be commissioned with an interval of four to five month each, after the commissioning of the first unit.

 