The first unit of the Srisailam Left Bank Hydro Project was commissioned and synchronized to the State power grid on 27 April 2001.

 

The Rs.2,325 crore project involves the construction of six generating units of 150 MW each. The underground project is situated 250 metres below ground level in the midst of the Rajiv Tiger Reserve Forest on the banks of the River Krishna in the Mahaboobnagar district of Andhra Pradesh. The project is being implemented by Andhra Pradesh Power Generation Corporation.

 

The second unit of the power plant is expected to be ready by August 2001, and the remaining four, by December 2002.