Srisailam Hydel Project: Fifth unit commissionedIllustrative image – not actual.

Andhra Pradesh Generation Corporation Ltd (APGenco) commissioned the fifth unit of the 900 MW (6 units x 150 MW) Srisailam Left Bank Power Project (SLBPP) on 28 March 2003, as per schedule. The sixth and final unit is likely to be commissioned by July 2003. The earlier four units were commissioned in April 2001, December 2001, April 2002 and November 2002, respectively. With this, the total hydel power generation capacity in the state has gone up to 3,432 MW.

 

All the six units of the SLBPP are likely to be operational during the ensuing monsoon period, depending on the water levels of the Srisailam reservoir.