Illustrative image – not actual.The housing project will spread over 14,993.75 sq mtr of plot area and 57,475.79 sq mtr of built-up area of land. It comprises three blocks -- Block A with 101 flats, Block B of 138 flats, Block C has 120 flats, each having cellar+G+five floors. The Amenities Block will accommodate cellar+G+four floors.
The project will be backed by modern amenities and comprise sewage treatment plant (STP) with a capacity of 250 klpd. In the latest update shared with Projects Today, it was disclosed that foundation work was underway. The project completion was scheduled for December 2021.