Illustrative image – not actual.SREI International Finance plans to invest Rs.34.05 crore in the 220 MW barge-mounted gas based Tanir Bavi power project coming up on the Gurpur river in Mangalore. The funds would be invested in one stand-by engine required for maintenance of the floating power plant.
The project, christened Mangalore II, is being promoted by GMR Group and its associates and the US based PSEG Group, while Tanir Bavi Power Co. is implementing it.
The project is estimated to cost Rs.900 crore and will
have a debt-equity ratio of 70:30.
The project will have four engines with 90 per cent
plant availability guaranteed. The stand-by engine will be used to cut
on-schedule outages. The plant will also have four turbines of 55 MW each with
a combined cycle starting on naphtha. The import component of the project will
be 70 per cent.
The first phase of the project is expected to start
by April 2001.
The project was approved by the Government of Karnataka
in 1995. The signing of the power purchase agreement and the escrow cover were
completed in 1997 and 1999, respectively.