Power Grid Corporation of India
(PGCIL) proposes to set up a special purpose vehicle (SPV) to undertake all
clearances for a designated project before transferring it to the developer.
The clearances would include land, environment and forest clearances and right
of way. The SPV route would be applicable to all power transmission projects involving
private sector participation.
PGCIL has taken up two models through the SPV route. In the first case, independent power transmission companies would be allowed to take up 100 per cent equity in projects. In the second case, PGCIL would take up a 26 per cent equity stake. Projects would be awarded through the competitive bidding route. PGCIL, which would be the sole owner of the SPV, would allow the winning bidder to buy it out. The purchasing company would be responsible for owning, operating and maintaining the project. Whichever model succeeds would be implemented for forthcoming major transmission projects.