Southern region of RailTel's OFC project likely to be up by June 2002Illustrative image – not actual.

The southern region of the first phase of RailTel Corporation's optic fibre cable (OFC) project is likely to be up by June 2002, three months behind schedule. This delay is reportedly, a result of the Railways handling other works of the Southern Railway besides the RailTel project.

 

The southern region of the project’s first phase is estimated to cost Rs.38 crore. It comprises laying OFC between Chennai-Gudur section covering about 136 km (costing Rs.9 crore), Chennai-Arakkonam-Renigunta section covering 135 km (Rs.7 crore) and Bangalore-Dharmavaram section for about 210 km (Rs.22 crore).

 

About 120 km of OFC has been laid on the Bangalore-Dharmavaram section and is expected to be completed as per schedule by March 2002. However, the contracts for the other two sections have just been awarded and are expected to be completed by June 2002.

 

RailTel’s entire project envisages laying 35,343 kms of OFC along the railway track across the country. Of this 10,020 kms would be laid in the first phase. So far, cable laying works for about 2,589 kms have been completed. The project cost is estimated to be around Rs.7 lakh per km (i.e. approx. Rs.2,474 crore for the entire project).

← All latest storiesBack to top →