Illustrative image – not actual.Southern Railways’ (SR) optic fibre cable (OFC) project in the Villupuram-Tiruchchirappalli section of Tamil Nadu would be commissioned by October end 2000. The project, covering 178 km comprising 24 stations, was sanctioned in 1998-99 with an estimated cost of Rs.14.05 crore.
Under the project, SR laid 24
fibres OFC to cater to the future communication needs. Of the 24 fibres, four
fibres would be retained by SR for its own communication needs. Another four
fibres would be retained by it as a stand by. The remaining 16 fibres would be
sold to ISPs and cellular operators, either on a revenue sharing basis or on a
fixed fee basis.
Apart from this, SR has also laid
four copper cables in this section to facilitate emergency communication and
communication between level crossings. These cables would improve the
performance of block signaling.
The SR has also commissioned
synchronous digital hierarchy equipment of 155 MB, which would have a capacity
to carry 1890 voice channels simultaneously. Here too there would be excess
capacity of 100 MB, which SR is likely to lease out.