Minister of State (I/C), Ministry of Housing and Urban Affairs, Hardeep Singh Puri; Union Minister for Chemicals and Fertilizers D V Sadananda Gowda; and Chief Minister of Karnataka, B S Yediyurappa, inaugurated six-km long southern extension line under Phase-2 of Namma Metro from Yelachenahalli to Silk Institute Metro stations by flagging off the train on 14 January 2021.
The inauguration of the Metro extension line and the FOBs is a step towards the goal of Bengaluru Mission 2022 to enable faster commute and smart mobility options in the city.
The Bangalore Metro Rail Project Phase-2 covers a route length of 74 km with 62 stations and consists of extensions to both Purple and Green lines of Phase-1 in all the four directions totaling 34 km and two new lines viz Gotigere-Nagawara for a route length of 21 km and R V Road- Bommasandra for a route length of 19 km.
The project is being implemented at a cost of Rs 30,695 crore.
The extension has five new stations beyond Yelachenahalli Metro Station on the currently operational line, namely Konanakunte Cross, Doddakallasandra, Vajarahalli, Thalaghattapura and Silk Institute.
The extension is six-km long elevated Metro at the southern end of the currently operational 24.2 km long green (north-south) line.
With this extension, North-South Corridor will become 30.2 km long. The elevated portion comprises 213 spans.
The work involves 1,032 piles, 223 piers and 1,998 segments for superstructure and 665 girders in stations.
Major materials like concrete quantity of 2,10,965 cum and 20,500 tonne of steel have been used in the works. Moreover, for electrification works, signalling and telecommunications, apart from state-of-the-art equipment, 765 km of cable and wires of various sizes have been laid.
Some of the features of the Metro are -- each station is equipped with eight escalators and four elevators, totalling to 40 escalators and 20 elevators respectively; energy-efficient LED lights at all five stations; for physically and visually challenged persons, facilities like ramps, lifts, separate toilets, tactile routing and earmarked space in trains are provided.
All five stations of this extension line are going to have roof top solar power with total 1.2 MW capacity. The installation of the solar power plants is targeted for completion by March 2021. This is the first time Bangalore Metro is establishing the capacity for solar power.
All the stations are provided with entry/exits opening onto the newly provided service road. Bus bays, pickup and drop area for taxi and autos are all earmarked in the service roads.
Exclusive mode change service lanes have been created on both sides of the five stations to co-locate bus stands and provide space for intermediate public transport (IPT).
The Bangalore Metro has deployed state-of-the-art technology for Automatic Fare Collection (AFC) System, which supports travel using open loop NCMC One Nation One Card, in the five stations inaugurated.
The AFC system at 40 stations of the currently operational 42 km long network is also being upgraded for NCMC.
The NCMC-based ticketing service, including in Phase-1 Lines, is targeted to be available for travel within 15 August 2021.
Thereafter, in the entire Metro network of 55 km in Bengaluru, including the western extension, commuters can use Rupay card or any other NCMC compliant bank card to pay for their travel.