South Central Railway to begin operations on first stretch of MMTS Phase-IIIllustrative image – not actual.

The South Central Railway (SCR) will soon begin operations on the first stretch of the Multi-Modal Transport System (MMTS) Phase-II between Tellapur and Ramchandrapuram of a distance of about six km.

The railway line was supposed to be opened by December 2017. However, it will take another two months for it to become operational.

The work has been completed as per schedule, including laying a single track and electrification. The commissioner of rail safety and other regulatory authorities are expected to complete the inspections in the course of the next two months.

The next railway line to be completed as part of the project will be Bolarum-Medchal covering a distance of 12.5 km. The railway electrification work is expected to be completed by 31 January 2018.

The ongoing doubling and electrification work on 12 km of Moula Ali-Ghatkesar line is scheduled for completion by March 2018.

The Falaknuma-Umdanagar covering a distance of 12 km is scheduled for completion by December 2018. The doubling and electrification work on this line is underway.

Except for the Sanatnagar-Moula Ali line, the SCR will be opening different lines for commercial operations in 2018 for MMTS Phase-II in phases.

The Indian Railways have spent Rs 450 crore, and Rs 240 crore is due from the state as it has released only Rs 40 crore so far.