South Africa’s Clanwilliam dam to be completed by 2023Illustrative image – not actual.
The construction works on South Africa’s Clanwilliam dam are set to be completed by March 2023. The Clanwilliam Dam, a concrete gravity dam is situated on the Olifants River, near Clanwilliam, Western Cape, South Africa.

Currently work is being carried out on wall-raising of the dam which will see the capacity of the dam double after the existing wall is raised by approximately 13 mtr. The work is being carried out at an investment of USD 229 million. The original walls of the dam were built early 1935 hence they require maintenance to sustain its integrity.

Additionally, the National Department of Water and Sanitation has seen significant progress in the Phase-I of the project with the relocation of the N7 highway in the region of the dam.

Doubling of the capacity of the dam will allow more irrigation in the region with an additional 5,500 ha. This could see about 3,800 jobs created thereby enhancing the economy of the Western Cape.

← All latest storiesBack to top →