South Africa govt installs turbines at Kangnas Wind FarmIllustrative image – not actual.
The government of South Africa has completed installation of 61 wind turbines at Kangnas Wind Farm. The final nacelle and blades have been installed at Kangnas Wind Farm two weeks ahead of schedule and on budget.

Local Northern Cape communities will have a new source of clean electricity when the wind farm enters commercial operations later this year. The Kangnas Wind Farm project is situated approximately 46 km outside of Springbok, in the Northern Cape’s Nama Khoi Municipal area, South Africa.

With Concor and Concor Consortium as contractors, the USD 246 million worth wind farm has been constructed on a 3,591 ha piece of land, and will consist of a total of 61 wind turbines supplied and installed by Siemens Gamesa Renewable Energy, each with a capacity of 2.3 MW.

The turbines are 168 mtr high and are equipped with a three-blade rotor with a diameter of 108 mtr each. Every single turbine is mounted on a 115 mtr high tubular steel tube tower and will run at an average speed of 15 rpm.

The project also includes the construction of 12.8 km long 132 kV dual circuit overhead line and a substation to increase the voltage from 132 kV to 220 kV. It is from these installations that the electricity will be fed into the national grid in order to power up to 1,20,000 households in the country.

The wind farm is expected to generate 140 MW clean renewable power from its 61 wind turbines during operations. It is also projected to get rid of approximately 5,50,000 tonne of carbon emissions every year from the day it goes live. Mainstream Renewable Power, a Sweden-based independent power producer (IPP), is in charge of the development.