Illustrative image – not actual.The development will occupy 40 acre of land. The Ranchi Municipal Corporation had signed a concession agreement with Ranchi MSW for a concession period of 25 years in 2016. The overall project investment is valued at Rs 277 crore.
The project under construction from the past three years was expected to be ready by June 2019. However, as per the latest update with Projects Today, the completion has been re-scheduled for September 2019.
Around 60 percent work on solid waste management unit has been completed till date and work on waste-based power unit was yet to commence.