Solar park unveiled in GujaratIllustrative image – not actual.

Narendra Modi, Chief Minister of Gujarat launched a solar park in Patan district.

The proposed park to be developed in phased manner has 500 MW generation capacity. The Phase I being developed by Gujarat Power Corporation (GPCL) is spread over 2,089 ha. It will have altogether 15 solar power generation companies producing 176 MW on the land leased out to them for 30 years. Gujarat Energy Transmission Corporation will set up a pooling station.

The overall project cost in Phase I is estimated at Rs 1,287 crore, including Rs 351 crore towards the cost of land and power infrastructure and evacuation facility worth Rs 624 crore. The Planning Commission has approved a one-time additional central assistance of Rs 210 crore for development of the solar power park. The Asian Development Bank (ADB) has also approved a soft loan of $100 million (approx Rs 450 crore) for the project.