Solar Park Scheme gets extensions from MNRE till FY26Illustrative image – not actual.

The Ministry of New and Renewable Energy (MNRE) has extended the date of the 'Development of Solar Parks and Ultra Mega Solar Park Projects' scheme till FY26.

The scheme, which was initially scheduled to end in March 2024, was introduced in December 2014 to support states and union territories to establish solar parks at various locations.

Under the scheme, the ministry will provide central financial assistance (CFA) of up to Rs 25 lakh per solar park for preparing a detailed project report (DPR). Apart from this, CFA of up to Rs 20 lakh per MW or 30 percent of the project cost, including grid-connectivity cost, is also provided to achieve the milestones stipulated in the scheme.

Further, out of the 57 solar parks with an aggregate capacity of 39.28 GW, only nine have been completed, and another eight have been partially completed as of February, 2023.