Solar manufacturing tender gets bids after delaysIllustrative image – not actual.
India’s first solar manufacturing tender with linked power plant has received bids after a delay of close to two years and several extensions. As per the latest tender floated by the Central government with several modifications, three companies have submitted their bids.

The government invited bids for 2,000 MW solar manufacturing and 6,000 MW linked solar power plant, which the industry oversubscribed. Adani Green Energy submitted bid for 1,000 MW manufacturing and 4,000 MW power plants; Azure Power submitted bid for 500 MW manufacturing and 2,000 MW power plants. Navyug Power submitted a bid similar to Azure Power. The financial bids will be opened in a few weeks.

The Solar Energy Corporation of India (SECI) under the aegis of the Ministry of New and Renewable Energy floated the tender. The success of the tender comes after the Centre relaxed norms for bidding. With a hope to attract more investor interest, the tariff cap was set at Rs 2.75 per kWh (unit).

The government increased the capacity of the tender with 500 MW manufacturing unit with power generation plant of 1,500 MW. A total of four such projects were put under the bidding process. A company can bid for one or all four.

The Centre also allowed using imported solar modules for the power plant and not necessarily to be sourced from the manufacturing unit set up by the company. This was mandatory earlier. Another addition in the tender is regarding manufacturing wherein companies can submit bid for setting up manufacturing of ingots and wafers as well as solar cells and modules.