Illustrative image – not actual.Progress on the 504 km long Goa-Mumbai highway has been very slow. So far, only 57.50 km of bituminous road has been laid between Panvel and Indapur and between Zarap and Patradevi sections.
Sixty per cent work on the Rs 517 crore Mandovi bridge on NH 17 has been completed and the target for completing the work is 31 May, 2018. There is, however, hardly any progress on the Rs 936 crore Zuari bridge as only one percent construction has been achieved while the target date is November 23, 2019.
The progress is 36 percent in case of the Talpona, Galgibaga and Maxem bridges as part of the Canacona bypass worth Rs 280.16 crore, with the target date for completion being 6 December, 2017.
The cement concrete road has been proposed on the remaining part of the highway as the new four lane or two lane carriageway, while on the existing two lane carriageway, a bituminous road has been proposed.